Intumescent coating should be inspected as a complete, specified fire-protection system—not judged by colour or appearance alone. Before handover, project teams should confirm that the correct primer, reactive coating and topcoat have been applied to the identified steel members; that measured dry film thickness matches the project loading schedule; that defects and repairs are closed out; and that traceable records are ready for the building’s fire safety information pack.
This matters because two beams that look identical can require different coating thicknesses. The requirement can vary with the fire-resistance period, steel section, section factor, design temperature, exposure and the tested or assessed scope of the selected product. A visual check is useful, but it cannot establish those facts on its own.
A useful inspection should answer six questions:
For the wider regulatory context in England, Approved Document B gives statutory guidance supporting the fire safety requirements of the Building Regulations. The project fire strategy and specification should translate those requirements into a defined fire-resistance period and protection approach for the structural frame.
Start with an approved coating or loading schedule, not a generic thickness target. It should identify the steel members, section sizes or section factors, required fire-resistance periods, product and required dry film thickness (DFT). Drawings and member marks must be coordinated so the installer and inspector are checking the same item.
If the steel design changes, the coating requirement may change too. Substituted sections, added connections, cellular beams, partial exposure or revised fire strategy assumptions should therefore trigger a design review—not an improvised site decision.
Intumescent protection is a system. The substrate preparation, anti-corrosive primer, reactive basecoat and decorative or protective topcoat must be compatible with one another and within the coating manufacturer’s tested or assessed system. Record product names, batch details and relevant technical data sheets. Where steel arrives pre-primed, obtain the primer identity and thickness records before applying the intumescent layer.
Unknown existing paint is a particular risk during refurbishment. Do not assume a new intumescent product can simply be applied over it. Condition, adhesion and compatibility need competent assessment, with manufacturer input where required. Midsummer’s overview of intumescent coatings for structural steel explains the role of the system within passive fire protection.
Before coating starts, steel should be prepared to the specified standard and free from contamination, moisture, loose material and corrosion that could undermine adhesion. During application, record air temperature, steel temperature, relative humidity and dew-point margin in line with the product data sheet. Also check storage conditions, mixing requirements, recoat windows and curing times.
These records are not paperwork for paperwork’s sake. Poor conditions can produce soft coating, delayed curing, blistering, loss of adhesion or premature failure even where the final thickness reading appears acceptable.
Wet film thickness checks help the applicator control each coat while work progresses. They can identify thin or excessive application early, before the area moves on. However, wet readings are an application control; final verification relies on properly taken DFT readings after the coating has cured sufficiently.
DFT readings should be taken with suitable calibrated equipment using an agreed inspection method. The report should identify the gauge, calibration checks, date, inspector, member reference, faces measured and the individual or summarised results required by the specification. Primer thickness needs to be accounted for so the result represents the intumescent layer correctly.
There is no responsible universal “pass” thickness for every beam. Compare readings with the approved loading schedule and the manufacturer’s requirements for that member. Both under-application and excessive build can be problematic. Low or anomalous readings should be mapped, investigated and rectified using an agreed repair method before later finishes hide the issue.
The Fire Protection Association’s good practice guide for intumescent coatings covers thickness control, inspection, records and rectification in more detail.
Do not limit the inspection to the broad, easy-to-reach faces of beams and columns. Check:
Photograph defects and completed repairs against a drawing grid, room, level or member mark. “Beam near the stairs” is not a location system that survives handover.
A complete evidence pack should enable the client, responsible person and future maintenance team to understand what was installed, where it is and how it should be maintained. Depending on the project, include:
For relevant building work, Regulation 38 of the Building Regulations 2010 requires fire safety information to be provided to the responsible person. The regulation describes information relating to design, construction, services, fittings and equipment that will help them operate and maintain the building with reasonable safety. Intumescent coating records should be organised with that practical purpose in mind.
If the project would benefit from controlled factory application, read about off-site intumescent coating. Earlier application can improve process control and reduce congestion on site, but transport damage, site connections and remedial coating still need a defined inspection and repair process.
Quality is easier and cheaper to prove in stages. Agree responsibilities under the project’s management arrangements, define inspection hold points before work starts and make the records part of each application area’s completion criteria. The HSE’s CDM 2015 guidance provides an official overview of construction dutyholder roles and responsibilities.
Dry film thickness is the measured thickness of a cured coating. For intumescent protection, it is checked against the approved requirement for the relevant steel member and coating system.
No. DFT is important, but the review should also cover the design basis, product system, primer compatibility, substrate preparation, application conditions, curing, continuity, damage and traceable records.
Inspection should be staged: before application, during coat build-up, after curing, after repairs and before areas are concealed or handed over. Waiting until practical completion can make meaningful checks difficult and remedial work expensive.
Often it can, but the repair must follow an approved method suitable for the original system and damage. The cause and extent should be assessed, and the completed repair recorded and reinspected.
The inspection should be completed by people with the competence required for their role and the project’s specified level of independence. Responsibilities, acceptance criteria and escalation routes should be agreed before application starts.
Intumescent coating is easiest to verify while the steel, records and responsible trades are still accessible. Midsummer Fire Protection supports commercial projects with evidence-led intumescent coating services and wider passive fire protection expertise. Contact Midsummer Fire Protection to discuss certified passive fire protection support, inspection requirements or an intumescent coating package for your project.