Fire stopping during an occupied refurbishment should be planned before the first ceiling tile is lifted or service opening is formed. The practical goal is to keep compartment lines, protected routes and other fire precautions effective while work progresses—not simply to seal penetrations at the end. That means confirming the existing fire strategy, controlling every new opening, coordinating temporary precautions and recording each completed installation.
This guide gives commercial property managers, facilities teams, principal contractors and specialist subcontractors a workable process for offices, retail premises, healthcare environments and other occupied buildings in England. It is general guidance rather than a substitute for project-specific fire engineering, a suitable and sufficient fire risk assessment, or the manufacturer’s tested installation detail.
Refurbishment creates a moving fire-safety risk. Ceiling voids are opened, partitions change, cables and pipes cross fire-resisting construction, and contractors may work across several floors at once. Meanwhile, staff, visitors, tenants or vulnerable occupants may remain in the building.
The HSE’s fire safety in construction guidance explains that refurbishment work should take account of the existing building, including concealed voids or incomplete compartmentation, and consider how work affects existing general fire precautions. The Regulatory Reform (Fire Safety) Order 2005 also requires a suitable and sufficient assessment of fire risk and a review where significant changes make the existing assessment potentially outdated.
For an occupied project, the key mistake is treating fire stopping as a late finishing trade. If compartmentation is breached for days or weeks without controlled temporary arrangements, the building may not perform as its current fire strategy assumes.
Before opening up construction, gather the information that defines what must be protected. This may include the current fire strategy, fire risk assessment, compartmentation drawings, evacuation arrangements, previous survey reports, service information and records from earlier fit-outs.
Confirm which walls and floors are intended to resist fire, where protected stairs and corridors run, and where risers, shafts, fire doors, cavity barriers and dampers contribute to the overall strategy. A general layout drawing is not enough if it does not identify fire-resisting elements and their required performance.
If records are incomplete, inconsistent with the building or silent about concealed areas, commission a proportionate fire compartmentation survey before finalising the works package. This reduces the chance of discovering widespread defects only after ceilings, finishes and programme commitments are in place.
A permit-to-penetrate process turns an informal site activity into a controlled change. Every planned opening through fire-resisting construction should have an owner, location, service description and agreed close-out route before drilling or cutting begins.
The permit should link the opening to a drawing or unique reference, identify the element being penetrated, record the service type and dimensions, and state who is responsible for temporary and permanent reinstatement. It should also prevent uncontrolled changes—such as adding more cables to a sealed opening—without checking that the proposed configuration remains supported by the selected system evidence.
This is particularly useful in multi-contractor programmes. Electrical, data, mechanical and fit-out teams can otherwise create penetrations faster than a fire-stopping contractor can identify or trace them. A permit register gives the principal contractor and building team one view of what is open, what is temporarily controlled and what has been permanently closed.
The permanent installation matters, but so does the period between opening and close-out. Temporary arrangements must come from the project’s risk assessment and competent fire-safety advice; there is no universal detail that suits every occupied building.
Planning may need to address the size and duration of openings, simultaneous work areas, temporary separation, housekeeping, hot works, isolation procedures, escape-route protection, alarm or detection changes, out-of-hours working and communication with building users. Where work affects the assumptions behind an evacuation strategy, the responsible parties should review those arrangements before proceeding.
The Government’s fire risk assessment guide for offices and shops stresses the need for responsible persons in multi-occupied buildings to co-operate and co-ordinate. In practice, landlords, managing agents, tenants and contractors should understand who controls each area and who is communicating changes that could affect others.
Good fire stopping is not “red sealant around a hole”. The proposed solution must suit the service, opening, supporting construction, orientation, required performance and movement conditions. Plastic pipes, metal pipes, cable bundles, cable trays, ducts and mixed-service openings behave differently in fire and may require different system components.
Before installation, check the project specification and relevant test or assessment evidence. Confirm that the wall or floor construction, service material and size, aperture dimensions, annular space, backing, fixings, seal depth and other critical details fall within the supported field of application. Product substitutions and mixed-manufacturer assemblies should not be accepted on convenience alone.
A specialist fire-stopping installation team should be brought into coordination early enough to review difficult details—not handed an inaccessible bundle of openings after services are complete.
Occupied projects often have short work windows, security restrictions and areas that cannot be taken out of use together. Build these constraints into the fire-stopping programme rather than letting them become reasons for incomplete records.
For more detail on evidence before access is lost, see Midsummer’s guide to recording service penetrations before ceilings close.
The record needs to help a future building manager, inspector or contractor understand what was installed and where. A folder of unlabelled photographs does not achieve that.
For each installation, retain a unique ID; building, floor and room or grid location; marked-up drawing reference; the compartment element and required performance; opening and service details; selected system and supporting product documentation; installer and inspection details; dates; and clear before, during and after photographs. Record approved deviations and design decisions rather than allowing them to live in email chains.
The Government’s accessible guide for people with duties under fire safety legislation says responsible persons should ensure compartmentation remains effective, particularly after works that may penetrate or damage it, and arrange competent repair where defects are found. Reliable close-out records make those later checks far more useful.
Potentially, but only where a suitable risk assessment and phased plan show that occupants, escape routes and fire precautions can be protected throughout the work. The answer depends on the building, affected compartmentation, occupancy and scope—not on a blanket rule.
No. A fire risk assessment considers fire risk and precautions across the premises. A dedicated compartmentation survey can inspect the condition and continuity of fire-resisting construction in greater detail, including agreed accessible or intrusive areas.
The project should define competent responsibility for specification and approval. The selected detail must be supported for the actual construction, service configuration and required performance; it should not be chosen solely by product familiarity or colour.
Capture the opening and substrate before work, critical concealed stages during installation, and the finished labelled seal. Each image should link to a unique location on the penetration schedule and drawing.
Inspect at planned hold points before ceilings, riser doors, boxing or finishes hide the work. The completed building should also have an ongoing inspection and change-control regime appropriate to its risk assessment and fire strategy.
The cleanest occupied refurbishment is one where fire safety, services coordination and evidence requirements are agreed together. Early survey work and disciplined penetration control reduce rework, make tender scopes clearer and give the building team a usable record at handover.