Fire Stopping During Occupied Refurbishment: A Practical Guide for Commercial Buildings

By Midsummer Fire Protection

In This Article

Fire stopping during an occupied refurbishment should be planned before the first ceiling tile is lifted or service opening is formed. The practical goal is to keep compartment lines, protected routes and other fire precautions effective while work progresses—not simply to seal penetrations at the end. That means confirming the existing fire strategy, controlling every new opening, coordinating temporary precautions and recording each completed installation.

This guide gives commercial property managers, facilities teams, principal contractors and specialist subcontractors a workable process for offices, retail premises, healthcare environments and other occupied buildings in England. It is general guidance rather than a substitute for project-specific fire engineering, a suitable and sufficient fire risk assessment, or the manufacturer’s tested installation detail.

Why occupied refurbishment needs tighter fire-stopping control

Refurbishment creates a moving fire-safety risk. Ceiling voids are opened, partitions change, cables and pipes cross fire-resisting construction, and contractors may work across several floors at once. Meanwhile, staff, visitors, tenants or vulnerable occupants may remain in the building.

The HSE’s fire safety in construction guidance explains that refurbishment work should take account of the existing building, including concealed voids or incomplete compartmentation, and consider how work affects existing general fire precautions. The Regulatory Reform (Fire Safety) Order 2005 also requires a suitable and sufficient assessment of fire risk and a review where significant changes make the existing assessment potentially outdated.

For an occupied project, the key mistake is treating fire stopping as a late finishing trade. If compartmentation is breached for days or weeks without controlled temporary arrangements, the building may not perform as its current fire strategy assumes.

Start with the building’s fire strategy and compartment lines

Before opening up construction, gather the information that defines what must be protected. This may include the current fire strategy, fire risk assessment, compartmentation drawings, evacuation arrangements, previous survey reports, service information and records from earlier fit-outs.

Confirm which walls and floors are intended to resist fire, where protected stairs and corridors run, and where risers, shafts, fire doors, cavity barriers and dampers contribute to the overall strategy. A general layout drawing is not enough if it does not identify fire-resisting elements and their required performance.

If records are incomplete, inconsistent with the building or silent about concealed areas, commission a proportionate fire compartmentation survey before finalising the works package. This reduces the chance of discovering widespread defects only after ceilings, finishes and programme commitments are in place.

Questions to settle before work starts

  • Which compartment lines and protected routes will the works affect?
  • What fire-resistance performance is required at each relevant element?
  • Are the existing drawings reliable, and has a site check confirmed them?
  • Who can authorise a penetration, temporary opening or design change?
  • Who specifies the appropriate tested fire-stopping system?
  • How will occupants, escape routes and alarm arrangements be protected during each phase?
  • What evidence must be captured before work is concealed?

Use a permit-to-penetrate process

A permit-to-penetrate process turns an informal site activity into a controlled change. Every planned opening through fire-resisting construction should have an owner, location, service description and agreed close-out route before drilling or cutting begins.

The permit should link the opening to a drawing or unique reference, identify the element being penetrated, record the service type and dimensions, and state who is responsible for temporary and permanent reinstatement. It should also prevent uncontrolled changes—such as adding more cables to a sealed opening—without checking that the proposed configuration remains supported by the selected system evidence.

This is particularly useful in multi-contractor programmes. Electrical, data, mechanical and fit-out teams can otherwise create penetrations faster than a fire-stopping contractor can identify or trace them. A permit register gives the principal contractor and building team one view of what is open, what is temporarily controlled and what has been permanently closed.

Plan temporary fire precautions, not just permanent repairs

The permanent installation matters, but so does the period between opening and close-out. Temporary arrangements must come from the project’s risk assessment and competent fire-safety advice; there is no universal detail that suits every occupied building.

Planning may need to address the size and duration of openings, simultaneous work areas, temporary separation, housekeeping, hot works, isolation procedures, escape-route protection, alarm or detection changes, out-of-hours working and communication with building users. Where work affects the assumptions behind an evacuation strategy, the responsible parties should review those arrangements before proceeding.

The Government’s fire risk assessment guide for offices and shops stresses the need for responsible persons in multi-occupied buildings to co-operate and co-ordinate. In practice, landlords, managing agents, tenants and contractors should understand who controls each area and who is communicating changes that could affect others.

Match each penetration to supported system evidence

Good fire stopping is not “red sealant around a hole”. The proposed solution must suit the service, opening, supporting construction, orientation, required performance and movement conditions. Plastic pipes, metal pipes, cable bundles, cable trays, ducts and mixed-service openings behave differently in fire and may require different system components.

Before installation, check the project specification and relevant test or assessment evidence. Confirm that the wall or floor construction, service material and size, aperture dimensions, annular space, backing, fixings, seal depth and other critical details fall within the supported field of application. Product substitutions and mixed-manufacturer assemblies should not be accepted on convenience alone.

A specialist fire-stopping installation team should be brought into coordination early enough to review difficult details—not handed an inaccessible bundle of openings after services are complete.

Sequence access, inspection and close-out

Occupied projects often have short work windows, security restrictions and areas that cannot be taken out of use together. Build these constraints into the fire-stopping programme rather than letting them become reasons for incomplete records.

A practical installation sequence

  1. Survey the workface: confirm the compartment line, substrate, access and existing defects.
  2. Approve the detail: match the actual opening and services to the specified, supported system.
  3. Prepare safely: coordinate access, isolations, dust control and occupant protection.
  4. Record before installation: photograph the opening, services and supporting construction with its unique location reference.
  5. Install and inspect: follow the approved detail and capture critical stages that will no longer be visible.
  6. Label and close out: link the finished seal to the schedule, drawings and product evidence.
  7. Release the area: confirm temporary controls can be removed and ceilings or finishes can close.

For more detail on evidence before access is lost, see Midsummer’s guide to recording service penetrations before ceilings close.

What a useful fire-stopping record should contain

The record needs to help a future building manager, inspector or contractor understand what was installed and where. A folder of unlabelled photographs does not achieve that.

For each installation, retain a unique ID; building, floor and room or grid location; marked-up drawing reference; the compartment element and required performance; opening and service details; selected system and supporting product documentation; installer and inspection details; dates; and clear before, during and after photographs. Record approved deviations and design decisions rather than allowing them to live in email chains.

The Government’s accessible guide for people with duties under fire safety legislation says responsible persons should ensure compartmentation remains effective, particularly after works that may penetrate or damage it, and arrange competent repair where defects are found. Reliable close-out records make those later checks far more useful.

Common mistakes on occupied refurbishment projects

  • Opening first and designing later: the service route is fixed before anyone checks whether an evidenced fire-stopping configuration is achievable.
  • Assuming the drawings match the building: historic alterations and undocumented fit-outs can make old compartment plans unreliable.
  • Leaving temporary openings unmanaged: permanent close-out is programmed, but the risk created during the works is not.
  • Closing ceilings too early: key installation details become inaccessible before inspection and evidence capture.
  • Using appearance as acceptance: a neat red finish does not prove the underlying system is appropriate or correctly installed.
  • Losing responsibility between trades: the penetration is created by one contractor, enlarged by another and assumed to be somebody else’s problem.
  • Failing to update records: the final drawings and penetration schedule no longer reflect what is in the building.

Occupied refurbishment fire-stopping checklist

  • Confirm the fire strategy, risk assessment and compartment lines.
  • Survey uncertain or concealed areas before tender and programme lock-in.
  • Assign responsibility for penetrations, temporary controls and close-out.
  • Operate a permit and unique-ID register for relevant openings.
  • Review fire precautions whenever work changes the building’s risk profile.
  • Coordinate supported fire-stopping details before services are installed.
  • Protect inspection access and capture evidence before concealment.
  • Reconcile labels, photographs, schedules and marked-up drawings at handover.
  • Brief the building team on future inspection and change-control requirements.

Frequently asked questions

Can an occupied building remain open during fire-stopping works?

Potentially, but only where a suitable risk assessment and phased plan show that occupants, escape routes and fire precautions can be protected throughout the work. The answer depends on the building, affected compartmentation, occupancy and scope—not on a blanket rule.

Is a fire risk assessment the same as a compartmentation survey?

No. A fire risk assessment considers fire risk and precautions across the premises. A dedicated compartmentation survey can inspect the condition and continuity of fire-resisting construction in greater detail, including agreed accessible or intrusive areas.

Who should approve a fire-stopping detail?

The project should define competent responsibility for specification and approval. The selected detail must be supported for the actual construction, service configuration and required performance; it should not be chosen solely by product familiarity or colour.

What photographs should be taken?

Capture the opening and substrate before work, critical concealed stages during installation, and the finished labelled seal. Each image should link to a unique location on the penetration schedule and drawing.

When should fire stopping be inspected?

Inspect at planned hold points before ceilings, riser doors, boxing or finishes hide the work. The completed building should also have an ongoing inspection and change-control regime appropriate to its risk assessment and fire strategy.

Plan the work before compartmentation is disturbed

The cleanest occupied refurbishment is one where fire safety, services coordination and evidence requirements are agreed together. Early survey work and disciplined penetration control reduce rework, make tender scopes clearer and give the building team a usable record at handover.

If you are planning commercial refurbishment in London or the surrounding region, contact Midsummer Fire Protection to discuss passive fire surveys, fire-stopping coordination, installation and evidence-led close-out with an appropriately competent project team.

Get Started

Let's Discuss Your Fire Stopping Requirements

For enquiries, tenders or questions, please call our Head Office on 01536 211999 or contact our team via the enquiry form.

Why Choose Midsummer Fire Protection?

Friendly and professional
Accurate & expert guidance
No obligation quotes
Effective and trusted solutions
“A company renowned for workmanship, professionalism, and high quality. We aspire to exceed your expectations, on time, in time, every time”

Don’t Leave Your Fire Safety to Chance. Tell Us How We Can Help.

Our expert team are on hand to answer your questions or arrange a quotation for your requirements.
Enquiry Section (Single Col)
info@midsummerfirepro.co.uk · Free quote · Response within 24hrs
FIRAS & BMTRADA Certified | Nationwide | 1,000+ Sites
starenvelopephone-handsetchevron-down