From 30 September 2026, updated Approved Document B guidance in England supports evacuation lifts through a defined evacuation shaft: a protected stairway, evacuation lift and protected lobby working together. For project teams, the practical task is not simply to select a lift. The surrounding compartmentation, penetrations, doors, smoke control and evidence must be coordinated as one fire-safety system.
This guide explains what architects, principal contractors, M&E teams and passive fire specialists should check before walls and ceilings close. It focuses on the passive fire protection interfaces that can undermine an otherwise sound evacuation-lift design if they are left until late in the programme.
The 2026 amendments to Approved Document B take effect in England on 30 September 2026, subject to transitional provisions. The principal change is a recommendation for more than one common stair in blocks of flats with a storey 18 metres or more above ground level. The amendments also introduce design provisions supporting evacuation lifts.
Where an evacuation lift is provided, the amended guidance says it should sit within an evacuation shaft containing a protected stairway, the evacuation lift and an evacuation lift lobby. The lobby provides a protected waiting area, should connect directly to the protected stairway and should not be directly accessible from a flat, maisonette, storage room or electrical equipment room.
This is guidance for building work in England rather than a blanket retrospective instruction to alter every existing lift. Projects must establish which edition and transitional arrangements apply through their design and building-control team. The Government’s Approved Document B publication page should be checked for the current documents and any subsequent updates.
An evacuation shaft is only as dependable as its complete enclosure. Lift controls, power supplies, ventilation, smoke-control equipment, drainage and communications can all require services to pass through fire-resisting walls or floors. Every opening creates an interface that must be designed, installed and recorded correctly.
A generic instruction to “fire stop all penetrations” is not a design. The selected penetration-seal system must be suitable for the supporting construction, service type, opening size, configuration, required fire performance and expected movement. The installed detail should match its tested or assessed field of application. If the actual site condition sits outside that evidence, the issue needs technical review before installation—not a creative application of red sealant five minutes before handover.
Early coordination also protects the programme. A clear compartmentation strategy gives designers and trades a shared basis for locating fire-resisting elements, controlling penetrations and planning access for inspection.
Start with the approved fire strategy, architectural details and building-control information. Confirm the required fire resistance of the evacuation shaft, stair, lobby, doors and associated construction. Record which project stage and transitional provisions apply. Do not assume that a detail from another building, or even another shaft in the same development, is automatically suitable.
Produce coordinated drawings showing the full enclosure at every storey, including wall-to-floor junctions, head-of-wall conditions, façade interfaces, risers, lift entrances and lobby boundaries. Mark where services cross each fire-resisting element. The exercise should include concealed zones above ceilings and below raised floors—not just what is visible from the finished lobby.
List cables, cable trays, conduits, pipes, ducts, dampers and mixed-service openings. For each penetration, capture:
This turns fire stopping from a reactive finishing trade into a coordinated package. Midsummer’s guide to fire-stopping design coordination covers the wider pre-installation questions M&E teams should resolve.
The amended guidance links evacuation-shaft protection with smoke control. Any system protecting the staircase should provide the same level of protection to the evacuation lift and its lobby. Duct routes, dampers, builders’ work openings and control cabling therefore need joint review by the fire engineer, smoke-control designer, M&E contractor and passive fire contractor.
Check access for damper inspection and maintenance. A compliant component that cannot be accessed, commissioned or maintained is a future operational problem disguised as a completed installation.
Evacuation shafts attract late changes: controls, security, communications and landlord or tenant cabling. Use a permit-to-penetrate process so nobody drills through the protected enclosure without approval, an agreed tested detail and a route back to the fire-stopping register. Our practical guide explains how a permit-to-penetrate system can reduce uncontrolled damage during construction and later works.
Set formal hold points before ceilings, riser doors, wall linings or finishes hide the work. Inspection should compare the installed condition with the approved detail, not merely confirm that some fire-stopping material is present. Record deviations, corrective work and final acceptance.
Regulation 38 requires fire-safety information to be given to the responsible person at completion or occupation where it applies. For each fire-stopping installation around the evacuation shaft, retain location-linked photographs, product and system references, installer records, inspection status and approved changes. Keep the final records aligned with as-built drawings and the fire strategy.
The handover should also identify operational checks. Under the Fire Safety (England) Regulations 2022, responsible persons in high-rise residential buildings have duties concerning monthly checks of evacuation lifts and specified fire-fighting equipment; the Government provides a dedicated Regulation 7 lifts and equipment fact sheet.
A well-coordinated evacuation shaft package has one controlled set of drawings, a penetration schedule agreed before first fix, approved systems matched to real site conditions, named inspection hold points and a traceable change process. The passive fire contractor is involved while details can still be changed economically.
By contrast, warning signs include unlabelled openings, mixed services added after approval, unsupported services bearing on seals, generic product substitutions, missing photographs and discrepancies between the fire strategy and as-built layout. These are coordination failures, not cosmetic snags.
No. The amendments concern guidance for building work in England and include transitional arrangements. Existing buildings remain subject to their applicable fire-safety duties, but project teams should obtain competent advice rather than treating the new-build guidance as an automatic retrospective specification.
No. An evacuation lift is designed and managed for assisted evacuation under defined conditions. Its shaft, lobby, controls, power and operational arrangements form a coordinated system; relabelling an ordinary passenger lift does not make it suitable.
No. Suitability depends on the service, supporting construction, aperture, configuration and required performance. The installed system must be supported by relevant test or assessment evidence for the actual condition.
Before penetrations and interfaces are fixed into the coordinated design. Early involvement helps identify untested details, access constraints and trade clashes while they are still straightforward to resolve.
The 30 September 2026 changes make this a timely design and delivery issue for taller residential projects. The sensible response is not a last-minute product check; it is coordinated compartmentation, controlled penetrations, competent installation and evidence that follows the building into use.
Midsummer Fire Protection supports contractors, developers and building teams with certified fire-stopping installation, surveys and practical passive fire protection advice. Contact Midsummer to discuss evacuation-shaft interfaces, penetration schedules or inspection requirements before work is concealed.